The unloading steps of the slitting machine are completely and clearly divided into seven steps, and the slitting operation is standardized to prevent danger and misoperation:
1. First drive the shaft pulling trolley to the middle of the gantry crane to facilitate the lifting of the gantry crane.
2. The main operator raises the upper and lower supporting hooks, opens the winding cone, then lowers the supporting hooks, and uses the feeding device to send the winding shaft out of the machine.
3. The assistant uses the foam pad to block both ends of the material roll to prevent the end surface from being soiled or scratched. The assistant operator drives the trolley and the assistant lifts the material rolls taken up and down to the shaft pulling trolley and put them away.
4. After the coiling material has been lowered, the assistant assists the assistant operator to hoist the upper and lower coiling shafts with the tube cores to the feeding device for clamping, threading and continuing to start the machine.
5. Drive the shaft pulling trolley to the clamping position, clamp and pull the shaft.
6. After the material roll is put through the pipe, the assistant operator and the assistant will enter the frame together, and then take out the foam pads at both ends.
7. The assistant operator installs the tube core, and the assistant performs on-site sanitation.